Create a new Project to add supporting information and plan the
staffing and resources necessary to complete the Project. You can do this
during the New and Staffing phases.
This functionality is only available after you apply
the
mApp Solution.
Create a Project from the
CSM Desktop Client
or
CSM Browser Client
().
- Provide a name and select an Area from the drop-down list.
- Add a description (optional) and select a Requester.
- Select an Assigned Team and an Assigned To from the drop-down
lists.
- Select a Site from the drop-down list.
- Select a Portfolio and Program Name, if applicable.
The Portfolio, Program (if applicable), and Demand tabs are
links to the parent record information.
- The Planned Start and Planned End Date Fields are initially
populated from the associated fields in the Demand. Going forward, these dates
are populated based on the dates in the '0' Outline Task once Project Tasks are
imported. These will change with each import update as appropriate.
- Select Actual Start and End Dates.
- The Planned Effort Field is initially populated based on the
Resource Plans created in the Demand. As Project Tasks are created, the '0'
Outline Task provides the overall Planned Effort number (Effort Field in that
Summary Task).
- The Projected Remaining Effort Field is the Planned Effort minus
Actual Effort.
- The Actual Effort Field is based on the sum of Task Summary times
in the weekly Timesheets.
Provide supporting information in the Form
Arrangement.
- The Resource Plan tab contains Resource Items populated from the
Demand. You can add more Resource Items here, but it will not affect the Demand
baseline. Individual Resources are assigned in PPM Project Tasks.
- The Benefit Plans tab contains Benefit Items populated from the
Demand. You can add more Benefit Items here, but it will not affect the Demand
baseline.
- Enter additional Budget Items in the
Budget Items tab.
Once Budget Items transfer into a Project, fields labeled
Remaining below the quarterly budget breakdown figures show
the budget remaining after Cost Items have been applied. An alert icon

will identify any
Budget Items with Cost Items that exceed the budgeted amount.
- Enter Cost Items in the
Cost Items tab. Cost items that do not have an
associated Budget Item are identified with an alert icon. For more information,
see
PPM Cost Items.
- Enter Project Tasks in the
Project Tasks tab. It is recommended that
Project Tasks be created and updated with MS Project or Excel.
- Enter Issues in the
Issues tab. The
Open Issues area of Project Health will
reflect the number of open Issues for each health area based on the Issue Type.
For more information, see
PPM
Issues.
- The Risks tab contains Risks rolled over from the Demand. You can
add more Risks here, but it will not affect the Demand baseline.
- Enter Action Items in the
Action Items tab. For more information, see
Create PPM Action Items.
- Use the Change Orders tab to accommodate Project needs that will
affect scope, budget, or schedule.
- Use the Change Requests tab to track associated IT changes
associated with the Project (example: Install a new Server).
- Use the Project Task Import tab to import information exported
from Microsoft Project or Excel. For more information, see
Import Project Info.
This tab is only available on the
CSM Browser Client.
- Select
Save.
The Project Health Widget provides a view from the Project Manager
perspective of the three key areas that are indicators of overall project
health: Budget, schedule, and scope. You must manually change this Widget.