Minimum Production Deployment
•About the Minimum Production Deployment
•Hardware Requirements for the Minimum Production Deployment
•About Installing the Neurons for ITSM Components for the Minimum Production Deployment
About the Minimum Production Deployment
Customers with 10 or fewer users often want to minimize their hardware investment. With the minimum production deployment architecture, you install all Neurons for ITSM components, except for the Neurons for ITSM databases, onto a single server. We recommend that you install the Neurons for ITSM databases onto a separate Microsoft SQL server.
Example of Neurons for ITSM and Databases on Separate Servers
In this deployment, all three landscapes (development [staging], testing [UAT], and production) run on the same server. As a result:
•Any issues created during the development cycle might affect production users.
•You cannot perform preupgrade testing.
Hardware Requirements for the Minimum Production Deployment
The following are the hardware requirements for the Neurons for ITSM server:
• One server, either physical or virtual
•2 CPU
•4 GB memory
•200 GB hard drive
The following are the hardware requirements for the Microsoft SQL server where the databases reside:
• One server (we recommend a physical server)
•2 CPU
•8 GB memory
•1 TB hard drive
About Installing the Neurons for ITSM Components for the Minimum Production Deployment
Neurons for ITSM Components and Databases on Separate Servers shows a diagram of the recommended locations of the various Neurons for ITSM software components in this deployment.
Neurons for ITSM Components and Databases on Separate Servers